| Anaerobic Digesters and Boiler |
| Building Extension - Highland Creek |
| Toronto, Ontario |
|
| Client |
The Municipality of Metropolitan Toronto
Metro Works Department |
|
| Consultant |
| Procter & Redfern Limited |
|
| Project Completion Date |
| May, 2003 |
|
| Type of Contract |
| Lump Sum |
|
| Project Description |
| Stage one of the construction included the movement of the construction equipment onto the site and excavation of the site grounds. The excavation process will continue for a 2 to 3 month period. At the same, a tunnel was constructed from the plant entrance across Beechgorve Drive to the digesters’ location. |
|
|